BESS ECONOMICS · ANONYMISED CASE

Choosing storage duration with the full economics in view.

A developer needed to compare two-hour and four-hour storage without overstating merchant value or weakening the financing case.

THE QUESTION

Does the additional revenue from four-hour duration justify the additional capital and financing requirements?

THE WORK
  • 01

    Connected 8,760 observed hourly prices with dispatch assumptions and a 70% commercial capture factor.

  • 02

    Compared two-hour / 200 MWh and four-hour / 400 MWh configurations on a consistent cost and revenue basis.

  • 03

    Built project, debt and equity cash flows, including CFADS, debt-service coverage and downside scenarios.

8,760Observed hourly prices
2h / 4hDuration comparison
1.61×Base-case minimum DSCR
WHAT THE WORK ESTABLISHED

The reconstructed base case supported retaining two-hour duration unless incremental four-hour revenue could exceed the current merchant-value case. The four-hour CAPEX index increased to 164 while its first-year revenue index reached 150; returns and debt cover weakened.

Anonymised and analytically reconstructed case, not a live investment offer. Financing basis: 55% debt, 6.5% interest and ten-year equal-principal repayment. Figures describe the reconstructed case and are not return forecasts.